What Decisions Should Come Out of a Contractor WIP Review?

Ken Ndegwa
The schedule is on the table, and the meeting can still end without a decision. A useful WIP review should identify margin drift, under- and over-billing, cash timing, change-order exposure, cost-to-complete risk, and the owner responsible for each corrective action.
That is the agenda for an owner-led contractor in Dallas–Fort Worth. Work in progress is the unfinished-job view that should force those calls before the next payroll, draw, or backlog commitment. A spreadsheet nobody acts on is only a printout.
1. WIP is a decision meeting, not a spreadsheet
On the Friday the job-cost file is updated, the superintendent knows what is built, accounting knows what was coded, and the owner knows the bank balance. None of those facts says whether a job should be billed, re-estimated, or left alone.
In ordinary management use, work in progress is the work still underway. A useful schedule puts project status, costs to date, estimated cost to finish, approved contract value, and billings on one cutoff date. Fieldcrest's construction page uses that same set. The meeting starts when someone asks what will be different on Monday because of a line on that page.
Bring the jobs that can change a decision. A job belongs in the conversation when the estimated margin moved, billing and progress disagree, a change order is open, cash depends on the next application, or the cost to complete is old. Jobs that tie out, with a named owner for the next ordinary billing, can stay on the page without taking the hour.
See how Fieldcrest supports construction accounting and job visibility
2. Validate percent complete and cost to complete
Percent complete is only as good as the measure behind it. A field estimate and a cost-file estimate cannot both drive the meeting. Pick one measure, write down its inputs, and use the same cutoff as the costs and the billings.
For companies that report under U.S. GAAP, Topic 606 is narrower than a management worksheet. When a performance obligation is satisfied over time, paragraphs 606-10-25-31 through 25-33 say to measure progress with a single method, applied consistently to similar obligations, using an output method or an input method. Paragraph 606-10-25-35 says to update that measure as circumstances change. Paragraph 606-10-25-36 says revenue is recognized over time only when progress can reasonably be measured. Those paragraphs do not appoint a field percentage, a lender template, or a cost ratio as the method for every contractor. Whether a job is recognized over time depends on the contract and the reporting basis.
Generally applicable accounting practice: show costs incurred and estimated cost to complete separately, foot them to estimated cost at completion, and do not treat an unsupported remaining-cost figure as a settled percent complete.
Fieldcrest professional judgment: if nobody has walked the remaining work, or tied the remaining subcontracts and materials to that cost-to-complete number, the percent is not yet an input to a bid, a draw, or a hiring decision. Rebuild the estimate first. That is an operating rule for the review, not a conclusion about revenue recognition.
Ask three questions of the percent on the page:
- What measure produced it: units in place, a milestone, hours, or cost incurred compared with estimated cost at completion?
- What date was the cost to complete last revised, and who revised it?
- Which costs in the "incurred" column do not represent progress, such as stored material that is not installed or rework that was never in the estimate?
If the answer to the second question is a shrug, stop there. The rest of the WIP math will inherit that shrug.
3. Find margin fade and gain early
Job gross margin, as the construction page describes it, is the revenue left after direct job costs. On an unfinished job, use the margin implied by current estimated cost at completion. Costs so far can look tidy while the overrun sits in the work that remains.
Compare three margins on the same approved contract value: the bid or latest approved estimate, the prior review, and today's costs incurred plus today's cost to complete. Fade is a lower current margin than the margin you used to take the job. Gain is the reverse. Either one is a prompt to find the cause in labor, subcontract buyout, material price, unpriced extra work, or a stale cost to complete. The prior estimate is no longer the number to price the next job against until that cause is named.
The figures below are an illustration so the arithmetic can be checked. They are not a Fieldcrest client, a typical DFW job, or a statement of how revenue should be recognized.
| Item | Figure |
|---|---|
| Approved contract value | $480,000 |
| Estimated cost when the job was taken | $400,000 |
| Costs incurred | $250,000 |
| Estimated cost to complete | $190,000 |
| Estimated cost at completion | $440,000 |
| Billings to date | $310,000 |
| Pending change order, not approved | $35,000, kept out of the base value |
Cost progress is 250,000 divided by 440,000, or 56.8 percent of estimated cost at completion. Billing progress is 310,000 divided by 480,000, or 64.6 percent of approved contract value. The bid margin was 80,000 divided by 480,000, one sixth of contract value. The current estimated margin is 40,000 divided by 480,000, one twelfth. Estimated cost is $40,000 higher than the cost used to take the job. Those differences are the meeting. They are not a benchmark.
4. Separate billing timing from performance
Underbilling and overbilling describe a timing gap. They are not, by themselves, a GAAP caption or a verdict on the job.
In the illustration, billings have run ahead of cost progress. Cash may already be in the account for work the estimate says is still ahead. That can carry a payroll week, and it can also leave $190,000 of cost still to fund. The opposite gap, progress ahead of billings, can show a productive job whose cost has already left the bank.
Under the Topic 606 glossary, a contract asset is a right to consideration for goods or services already transferred when that right depends on something other than the passage of time. A contract liability is an obligation to transfer goods or services for which the customer has paid, or the amount is due. A line labeled underbilled or overbilled does not establish either caption. Contract terms, what has been transferred, and the reporting basis sit between the worksheet and the balance sheet.
For the meeting, keep four amounts apart on each job: approved contract value, progress under the chosen measure, amount billed, and amount collected. Retainage stays with the collection question. The construction page already treats it as an amount held until contract conditions are met, separate from other unpaid invoices.
Get the Contractor's Cash & Decision Toolkit. The job financial review and the decision register are the two pages that match this meeting: one for the job figures, one for who does what next. Get the toolkit
5. Surface change-order and collection exposure
A change order is a scope or price change. Topic 606 treats that change as a contract modification. Paragraph 606-10-25-10 says it may be called a change order, a variation, or an amendment, and that an unapproved modification stays on the existing contract. Paragraph 606-10-25-11 covers the next case: scope is approved and the price is still open. That open price is estimated as variable consideration. Paragraphs 606-10-32-11 through 32-13 include it only when a significant revenue reversal is not probable.
The management translation is narrower than a revenue conclusion. Use three columns:
- Approved. Scope and price are documented. This is the base contract value in the WIP.
- Scope approved, price open. Show the estimated price, label it as an estimate, and do not let it silently rewrite the margin.
- Not approved. Keep it off the base contract value. If the crew is already spending time or money on it, that spending belongs in cost and in the exposure list until there is an approval or a decision to stop.
Collection exposure is the cash version of the same discipline. Separate ordinary open invoices, retained amounts, and amounts the customer has disputed. A disputed change order is not a next-week receipt. This article does not interpret a pay-if-paid clause, a lien right, or a lender covenant. Those questions belong to the contract, counsel, or the lender's own definition.
6. Assign actions, owners and dates
The schedule has done its job when each exception has a person and a date. A cleaner layout without those assignments does not change payroll, billing, or the next bid. That is Fieldcrest's operating preference for this meeting, not a GAAP requirement and not a client result.
Use this decision table. It is an original Fieldcrest review aid. Fill it from the current schedule. Leave a row blank rather than inventing an owner.
| Signal on the WIP | Decision | Action | Owner | When |
|---|---|---|---|---|
| Current estimated margin is below the margin used to take the job | Find the cause before the next bid uses the old rate | Rebuild cost to complete by labor, subcontract, and materials | Project manager, confirmed by the owner | Before the meeting ends |
| Progress is ahead of billings | Decide whether approved work can be billed now | Send the application, or write why it cannot go | Project manager | Within five business days |
| Billings are ahead of progress | Decide whether remaining cost is funded | Compare cost to complete with cash and the next payroll | Owner | Before the next payroll |
| A pending change is sitting inside contract value | Decide which of the three columns it belongs in | Move unapproved amounts out of base contract value | Project manager | Same day |
| Cost to complete has no recent walkthrough or quote | Decide that the percent is not ready | Rebuild remaining quantities before the percent is used | Superintendent or project manager | Before the next review |
| An invoice or retainage balance has no follow-up | Decide who is asking for the cash | Record the release condition and the expected week | Owner or project manager | This week |
If a row matters and the owner cell is empty, carry it forward. Do not close it because the spreadsheet balanced. Margin drift without a revised cost to complete, a billing gap without a collection owner, and a change order left inside contract value are three different open items.
When the job-cost file, the billing log, and the cost to complete do not share a cutoff, the next conversation is a Financial Direction Review: a working session on what is limiting those decisions.
Ready for clearer financial direction? Book a Financial Direction Review with direct principal access. Book your review
General education only. This article does not provide individualized accounting, tax, legal, lending, or contract advice. A management WIP review does not determine revenue recognition, the tax method for a contract, or how a lender or surety will read a schedule.
Sources
- Financial Accounting Standards Board, ASU 2014-09 Section A, Topic 606 progress, contract asset, contract liability, and contract modification guidance — https://storage.fasb.org/ASU%202014-09_Section%20A.pdf
- Fieldcrest construction and contractor financial services — https://www.fieldcrestaccounting.com/app/industries/construction
- Fieldcrest Contractor's Cash & Decision Toolkit — https://www.fieldcrestaccounting.com/app/toolkit
- Financial Direction Review — https://www.fieldcrestaccounting.com/app/direction